OUR PROCESS

GLASS BOTTLE MANUFACTURING

01 DESIGN

With Design

This means the client already has their own design.

Without Design

Estimated time:
7 – 15 days
*Ask for our Design Device

02 DESIGN APPROVAL

Estimated time:
Approximately 7 business days

03 QUOTATION

Estimated time:
24 to 48 Business Hours

04 MOLD PRODUCTION

Estimated time:
8 – 10 Weeks

*It´s necessary to have the final design approved by the customer and the molds paid in full to begin production.

05 DOCUMENT DELIVERY

Estimated time:
24 Business Hours

  • Terms of Sale
  • Pallet Specification
  • Quality & Defects Manual

06 ORDER SCHEDULE

Estimated time:
Subject to availability


*To ensure the production dates, it´s required to submit a PO at least 8 weeks before the molds are ready.

07 GLASS PRODUCTION

Estimated time:
According to quantity

*To ensure the production dates, it´s required to submit a PO at least 8 weeks before the molds are ready.

08 MX, US, CA DELIVERY

Estimated time:
Up to 15 calendar days